Planning Advisory Committee
Minutes of
The meeting was called to
order at
Gary Loertscher, Ken Klink,
James Kniffin, Jerry Rabas,
kk opened the
meeting with a prayer and introductions were made.
Minutes of the
The building fund summary as
of
kk will check to
see if the Diocese Building Committee is meeting now that the bishop has issued
a building moratorium on new projects.
kk reported that
the diocese is conducting a major study. Parishioners will be asked to fill out
surveys on
Joe Stadelman (architect) and
Kevin Hammer (Findorff) have met twice with planning committee members to look
at possible modifications/cuts on the proposed project. The budget for building
the church, chapel, and office area as of
The planning committee
requests that the chapel be kept in the planning process/blueprints even though
it could possibly be deleted or delayed in the future.
The planning committee asked
AYA and Findorff to look at other possible changes to bring the cost in under
$4,000,000, but keep the chapel, provide A-V and ecclesiastical furnishings.
Those changes will be
presented at the next planning committee meeting on